Potable Water Storage and Distribution System Improvements Project
Project Description:
The major work consists of the furnish and installation of a 140,000-gallon bolted steel storage tank with a supplemental pressure transmitter and 6, 125 linear feet of 8-inch C900 potable water distribution pipeline with associated piping, fittings, valves, utility boxes, pressure reducing stations, fire hydrants. This Project also includes various site improvement such as the construction of a modular retaining wall, two chlorine dosing stations, perimeter fencing, asphalt pavement, earthwork, grading, electrical improvements and SCADA integration by ICAD.
Project Cost:
$2,919,497.08
Funding Source:
Urban and Multibenefit Drought Relief Grant Award: $8,545,000.00
Four part project includes: AWS Pipeline Relocation, AWS Treatment Plant Relocation, Hardrock Groundwater Well, and Tank & Pipeline Project.
Community Project Benefits:
- Twin 140,000-gallon tanks at Vernal Dr. and Merrell Rd.
- Replace failing and undersized water mains - 1 mile of new pipe is in the ground from the corner of Black Rd and Harper Rd to 18403 Harper Rd (approx. 5,000 linear feet).
- 6 hydrants and several valves are being added for improved service and resilience.
- Providing adequate fire flow through hydrants to Big Oak Flat
- Improve system functionality, reduce water losses
Engineer:
The Engineer for this Project is AM CONSUL TING ENGINEERS, INC. (Engineer), which is to act as Owner's representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.
Contractor:
Njirich and Sons, Inc.